Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100013110

Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II · Uruli Devachi, Pune · Vaishnavi Mahila Unnati Sanstha

Promised for 30 May 2022, extended once to 30 Nov 2023 — and that date has passed without the project marked complete on MahaRERA.

4 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 May 2022 to 30 Nov 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Nov 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate14 Jul 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100013110

Is Vaishnavi Mahila Unnati Sanstha Vaishnavi City Phase II delayed?

Yes. MahaRERA records a promised completion of 30 May 2022, revised to 30 Nov 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100013110. The completion date moved from 30 May 2022 to 30 Nov 2023.

Who is the promoter?

MahaRERA records Vaishnavi Mahila Unnati Sanstha as the promoter of P52100013110.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100013110.

Answers are generated from the record.

Data through29 Oct 2026, 01:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology