Registered1 extensionMahaRERA status: Certificate Signed

P52100009234

Jitendra Heritage - E 2 Building - Phase - 1 · Pashan, Pune · Jitendra Constructions

Promised for 28 Aug 2023, extended once to 31 Dec 2030, which is still ahead.

The revised date is 7 years and 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 28 Aug 2023 to 31 Dec 2030 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate1 Dec 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100009234

Is Jitendra Heritage - E 2 Building - Phase - 1 delayed?

Its completion moved from 28 Aug 2023 to 31 Dec 2030; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100009234. The completion date moved from 28 Aug 2023 to 31 Dec 2030.

Who is the promoter?

MahaRERA records Jitendra Constructions as the promoter of P52100009234.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100009234.