Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100008782

18 Latitude Commercial · Punawale, Pune · G D Square Developer

Promised for 30 Oct 2021, extended once to 31 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.

5 years past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Oct 2021 to 31 Dec 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate19 Aug 2017View
Extension certificate31 Oct 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100008782

Is 18 Latitude Commercial delayed?

Yes. MahaRERA records a promised completion of 30 Oct 2021, revised to 31 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100008782. The completion date moved from 30 Oct 2021 to 31 Dec 2023.

Who is the promoter?

MahaRERA records G D Square Developer as the promoter of P52100008782.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100008782.

Answers are generated from the record.

Data through28 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology