RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100008527

Lantana Court · Mohammadwadi, Pune · Landmark Ventures

Promised for 31 Aug 2018, extended once to 31 Aug 2019 — and that date has passed without the project marked complete on MahaRERA.

8 years and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Aug 2018 to 31 Aug 2019 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Aug 2019, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate19 Aug 2017View
Extension certificate10 Oct 2018View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100008527

Is Lantana Court delayed?

Yes. MahaRERA records a promised completion of 31 Aug 2018, revised to 31 Aug 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100008527. The completion date moved from 31 Aug 2018 to 31 Aug 2019.

Who is the promoter?

MahaRERA records Landmark Ventures as the promoter of P52100008527.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100008527.

Answers are generated from the record.

Data through29 Oct 2026, 03:04SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology