P52100006976
Atharva Shrishti, Phase 1, Wing A · Manjari Kh, Pune · Atharva Buildcon
Promised for 27 Jan 2021, extended once to 27 Jul 2022 — and that date has passed without the project marked complete on MahaRERA.
5 years and 9 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 27 Jan 2021 to 27 Jul 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 27 Jul 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100006976
Is Atharva Shrishti, Phase 1, Wing A delayed?
Yes. MahaRERA records a promised completion of 27 Jan 2021, revised to 27 Jul 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100006976. The completion date moved from 27 Jan 2021 to 27 Jul 2022.
Who is the promoter?
MahaRERA records Atharva Buildcon as the promoter of P52100006976.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100006976.