Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100006327

Playtor Rajgurunagar- Phase 2 · Rajgurunagar (Ct), Pune · Playtor Rajgurunagar Developers Private Limited

Promised for 30 Sep 2019, extended once to 30 Mar 2023 — and that date has passed without the project marked complete on MahaRERA.

7 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2019 to 30 Mar 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Mar 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate14 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100006327

Is Playtor Rajgurunagar- Phase 2 delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2019, revised to 30 Mar 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100006327. The completion date moved from 30 Sep 2019 to 30 Mar 2023.

Who is the promoter?

MahaRERA records Playtor Rajgurunagar Developers Private Limited as the promoter of P52100006327.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100006327.

Answers are generated from the record.

Data through25 Oct 2026, 01:48SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology