P52100005554
Kedari Landmark · Pune (M Corp.), Pune · Shree Ganesha Enterprises
Promised for 24 Aug 2019, extended once to 31 Mar 2026 — and that date has passed without the project marked complete on MahaRERA.
7 years and 2 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 24 Aug 2019 to 31 Mar 2026 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Mar 2026, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100005554
Is Kedari Landmark delayed?
Yes. MahaRERA records a promised completion of 24 Aug 2019, revised to 31 Mar 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100005554. The completion date moved from 24 Aug 2019 to 31 Mar 2026.
Who is the promoter?
MahaRERA records Shree Ganesha Enterprises as the promoter of P52100005554.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100005554.