RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100003765

Tropica Phase I · Pimpri Chinchawad (M Corp.), Pune · Om Developers Project Ravet

Promised for 31 Dec 2017 — that date has passed and MahaRERA does not mark the project complete.

8 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2017, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate13 Nov 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100003765

Is Tropica Phase I delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2017, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100003765.

Who is the promoter?

MahaRERA records Om Developers Project Ravet as the promoter of P52100003765.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100003765.

Answers are generated from the record.

Data through30 Oct 2026, 01:55SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology