Regulatory order: PROJECT NAME: GUARDIAN WIND SHIRE PHASE 1 (Regulatory Case No. 424 OF 2025) dated 10 March, 2026.
10 Mar 2026 · matched by RERA number
View order →RERA check · free, always
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Guardian Wind Shire · Nandoshi, Pune · Guardian Landmarks Llp
Promised for 30 Jun 2022 — that date has passed and MahaRERA does not mark the project complete.
4 years and 4 months past the original promise today.
Facts from the record. A flag is a reason to ask questions, not a verdict.
Regulatory order: PROJECT NAME: GUARDIAN WIND SHIRE PHASE 1 (Regulatory Case No. 424 OF 2025) dated 10 March, 2026.
10 Mar 2026 · matched by RERA number
View order →Yes. MahaRERA records a promised completion of 30 Jun 2022, which has passed, and the project is not marked complete.
Deedo holds 0 extension certificates for P52100001828.
MahaRERA records Guardian Landmarks Llp as the promoter of P52100001828.
1 MahaRERA order or list names P52100001828.
Answers are generated from the record.