RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100001581

Aum Trimurti C Building · Parvati, Pune · Built Up

Promised for 30 Dec 2019, extended once to 29 Dec 2021 — and that date has passed without the project marked complete on MahaRERA.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2019 to 29 Dec 2021 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Dec 2021, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate29 Jul 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100001581

Is Aum Trimurti C Building delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2019, revised to 29 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100001581. The completion date moved from 30 Dec 2019 to 29 Dec 2021.

Who is the promoter?

MahaRERA records Built Up as the promoter of P52100001581.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100001581.