RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100001522

Marvel Fria P1, P2, P3 Building · Wagholi, Pune · Pax Homes Llp

Promised for 30 Jun 2022, extended once to 30 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

4 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2022 to 30 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2024, has passed.
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate28 Jul 2017View
Extension certificate3 Apr 2024View

Orders 1

Regulatory order

Regulatory order: PROJECT NAME:Marvel Fria P1 P2 P3 Building (Regulatory Case No. 159 of 2024) dated 13 March 2024.

13 Mar 2024 · matched by RERA number

View order →

Questions about P52100001522

Is Marvel Fria P1, P2, P3 Building delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2022, revised to 30 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100001522. The completion date moved from 30 Jun 2022 to 30 Dec 2024.

Who is the promoter?

MahaRERA records Pax Homes Llp as the promoter of P52100001522.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P52100001522.

Answers are generated from the record.