RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52100001408

Aaditya Heights · Pune (M Corp.), Pune · Anand Developers

Promised for 31 Mar 2018 — that date has passed and MahaRERA does not mark the project complete.

8 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Mar 2018, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate28 Jul 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100001408

Is Aaditya Heights delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100001408.

Who is the promoter?

MahaRERA records Anand Developers as the promoter of P52100001408.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100001408.

Answers are generated from the record.

Data through25 Oct 2026, 01:37SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology