Seya · Parvati, Pune · Seya Pate Constructions Llp
Promised for 27 Sep 2020, extended once to 26 Mar 2022 — and that date has passed without the project marked complete on MahaRERA.
6 years and 1 month past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 27 Sep 2020 to 26 Mar 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 26 Mar 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100001129
Is Seya delayed?
Yes. MahaRERA records a promised completion of 27 Sep 2020, revised to 26 Mar 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100001129. The completion date moved from 27 Sep 2020 to 26 Mar 2022.
Who is the promoter?
MahaRERA records Seya Pate Constructions Llp as the promoter of P52100001129.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100001129.
Answers are generated from the record.