Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100000491

Siddhivinayak Pride · Manjari Bk, Pune · Sagar Dilip Rukari

Promised for 31 Dec 2017, extended once to 1 Feb 2018 — and that date has passed without the project marked complete on MahaRERA.

8 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2017 to 1 Feb 2018 (1 extension certificate on record).
  • Risk: The latest completion date on record, 1 Feb 2018, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 Jul 2017View
Extension certificate15 Jan 2018View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100000491

Is Siddhivinayak Pride delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2017, revised to 1 Feb 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100000491. The completion date moved from 31 Dec 2017 to 1 Feb 2018.

Who is the promoter?

MahaRERA records Sagar Dilip Rukari as the promoter of P52100000491.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100000491.

Answers are generated from the record.

Data through29 Oct 2026, 01:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology