RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
RegisteredMahaRERA status: Certificate Signed
P52000048827
Arkan Castle · Taloje Panchnad, Raigarh · Arkan Developers
Promised for 31 Dec 2027 and not extended so far.
1 year and 2 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P52000048827
Is Arkan Castle delayed?
Not so far. MahaRERA records a promised completion of 31 Dec 2027, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P52000048827.
Who is the promoter?
MahaRERA records Arkan Developers as the promoter of P52000048827.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52000048827.
Answers are generated from the record.
Data through23 Oct 2026, 02:14SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology