RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000048723

Harmony · Wahal, Raigarh · Vardhman Developers

Promised for 30 Jun 2024, extended once to 31 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2024 to 31 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate17 Jan 2023View
Extension certificate28 Jun 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000048723

Is Harmony delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2024, revised to 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000048723. The completion date moved from 30 Jun 2024 to 31 Dec 2024.

Who is the promoter?

MahaRERA records Vardhman Developers as the promoter of P52000048723.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000048723.

Answers are generated from the record.

Data through29 Oct 2026, 02:34SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology