RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000047771

Excelencia - Bungalow · Satirje, Raigarh · Iraah Lifespaces

Promised for 31 Dec 2024, extended once to 31 Mar 2026 — and that date has passed without the project marked complete on MahaRERA.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2024 to 31 Mar 2026 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Mar 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate28 Nov 2022View
Extension certificate7 Apr 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000047771

Is Excelencia - Bungalow delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2024, revised to 31 Mar 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000047771. The completion date moved from 31 Dec 2024 to 31 Mar 2026.

Who is the promoter?

MahaRERA records Iraah Lifespaces as the promoter of P52000047771.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000047771.

Answers are generated from the record.

Data through25 Oct 2026, 03:06SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology