Registered1 extensionMahaRERA status: Certificate Signed

P52000045952

Bhiva Tower · Taloje Majkur, Raigarh · Yash Developers Unit Of Vikrant V Raikar Huf

Promised for 30 Apr 2025, extended once to 30 Apr 2027, which is still ahead.

The revised date is 2 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Apr 2025 to 30 Apr 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate16 May 2024View
Extension certificate2 Jun 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000045952

Is Bhiva Tower delayed?

Its completion moved from 30 Apr 2025 to 30 Apr 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000045952. The completion date moved from 30 Apr 2025 to 30 Apr 2027.

Who is the promoter?

MahaRERA records Yash Developers Unit Of Vikrant V Raikar Huf as the promoter of P52000045952.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000045952.

Answers are generated from the record.

Data through30 Oct 2026, 02:44SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology