Promised for 25 Sep 2024, extended once to 30 Sep 2025 — and that date has passed without the project marked complete on MahaRERA.

2 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 25 Sep 2024 to 30 Sep 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Sep 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate22 Feb 2022View
Extension certificate30 Dec 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000033546

Is Prathamesh Soham delayed?

Yes. MahaRERA records a promised completion of 25 Sep 2024, revised to 30 Sep 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000033546. The completion date moved from 25 Sep 2024 to 30 Sep 2025.

Who is the promoter?

MahaRERA records Sachin Kamlakant Shringarpure as the promoter of P52000033546.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000033546.