Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P52000033464

Anand Villa · Bopele, Raigarh · Darshana Shantaram Mohite

Promised for 31 Mar 2024, extended once to 31 Dec 2027, which is still ahead.

The revised date is 3 years and 9 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2024 to 31 Dec 2027 (1 extension certificate on record).

Documents 2

Registration certificate20 Jul 2022View
Extension certificate14 Nov 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000033464

Is Anand Villa delayed?

Its completion moved from 31 Mar 2024 to 31 Dec 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000033464. The completion date moved from 31 Mar 2024 to 31 Dec 2027.

Who is the promoter?

MahaRERA records Darshana Shantaram Mohite as the promoter of P52000033464.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000033464.

Answers are generated from the record.

Data through22 Oct 2026, 01:55SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology