RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52000031836
Shree Krushnai-I · Ajivali, Raigarh · Shree Siddhivinayak Enterprises
Promised for 15 Sep 2023, extended once to 14 Sep 2024 — and that date has passed without the project marked complete on MahaRERA.
3 years and 1 month past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 15 Sep 2023 to 14 Sep 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 14 Sep 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52000031836
Is Shree Krushnai-I delayed?
Yes. MahaRERA records a promised completion of 15 Sep 2023, revised to 14 Sep 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52000031836. The completion date moved from 15 Sep 2023 to 14 Sep 2024.
Who is the promoter?
MahaRERA records Shree Siddhivinayak Enterprises as the promoter of P52000031836.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52000031836.
Answers are generated from the record.
