Registered1 extensionMahaRERA status: Certificate Signed

P52000020226

Sai Majestica · Bokadvira, Raigarh · Mewani Developers

Promised for 30 Dec 2024, extended once to 31 Dec 2026, which is still ahead.

The revised date is 2 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2024 to 31 Dec 2026 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate23 Jul 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000020226

Is Sai Majestica delayed?

Its completion moved from 30 Dec 2024 to 31 Dec 2026; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000020226. The completion date moved from 30 Dec 2024 to 31 Dec 2026.

Who is the promoter?

MahaRERA records Mewani Developers as the promoter of P52000020226.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000020226.

Answers are generated from the record.

Data through25 Oct 2026, 02:24SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology