Registered1 extensionMahaRERA status: Certificate Signed

P52000013152

Mount Ville · Kirawali, Raigarh · Samvid Life Spaces

Promised for 31 Mar 2019, extended once to 31 Dec 2026, which is still ahead.

The revised date is 7 years and 9 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2019 to 31 Dec 2026 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate14 Sep 2017View
Extension certificate15 Dec 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000013152

Is Mount Ville delayed?

Its completion moved from 31 Mar 2019 to 31 Dec 2026; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000013152. The completion date moved from 31 Mar 2019 to 31 Dec 2026.

Who is the promoter?

MahaRERA records Samvid Life Spaces as the promoter of P52000013152.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000013152.