Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000012810

Redwood Landmark · Pen (M Cl), Raigarh · Redwood Developers

Promised for 30 Dec 2021, extended once to 30 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.

4 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2021 to 30 Dec 2022 (1 extension certificate on record).
  • Caution: The latest completion date on record, 30 Dec 2022, has passed.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate14 Mar 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000012810

Is Redwood Landmark delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2021, revised to 30 Dec 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000012810. The completion date moved from 30 Dec 2021 to 30 Dec 2022.

Who is the promoter?

MahaRERA records Redwood Developers as the promoter of P52000012810.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000012810.

Answers are generated from the record.

Data through18 Oct 2026, 02:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology