Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000010101

Shalom Regency · Uran, Raigarh · Jacob George

Promised for 30 Sep 2019, extended once to 30 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.

7 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2019 to 30 Jun 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate24 Aug 2017View
Extension certificate31 Oct 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000010101

Is Shalom Regency delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2019, revised to 30 Jun 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000010101. The completion date moved from 30 Sep 2019 to 30 Jun 2023.

Who is the promoter?

MahaRERA records Jacob George as the promoter of P52000010101.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000010101.

Answers are generated from the record.

Data through29 Oct 2026, 01:46SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology