RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51900077429
The Empire Tower · Ward Abcd, Mumbai City · Samak Constructions Pvt. Ltd
Promised for 31 Dec 2029, extended to 30 Apr 2030, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2029 to 30 Apr 2030.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51900077429
Is The Empire Tower delayed?
Its completion moved from 31 Dec 2029 to 30 Apr 2030; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51900077429. The completion date moved from 31 Dec 2029 to 30 Apr 2030.
Who is the promoter?
MahaRERA records Samak Constructions Pvt. Ltd as the promoter of P51900077429.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51900077429.
Answers are generated from the record.