RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51900008501

Trevedia Vuepoint · Ward Gnorth, Mumbai City · S.B.Brothers Developers

Promised for 31 Jul 2018, extended once to 30 Sep 2018 — and that date has passed without the project marked complete on MahaRERA.

8 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jul 2018 to 30 Sep 2018 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Sep 2018, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate19 Aug 2017View
Extension certificate31 Jul 2018View

Orders 0

No MahaRERA order or list names this number.

Questions about P51900008501

Is Trevedia Vuepoint delayed?

Yes. MahaRERA records a promised completion of 31 Jul 2018, revised to 30 Sep 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51900008501. The completion date moved from 31 Jul 2018 to 30 Sep 2018.

Who is the promoter?

MahaRERA records S.B.Brothers Developers as the promoter of P51900008501.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900008501.

Answers are generated from the record.