RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51900005526

Allana Mansion · Ward E, Mumbai City · K. Living Estates Private Limited

Promised for 31 Mar 2019, extended once to 31 Mar 2024 — and that date has passed without the project marked complete on MahaRERA.

7 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2019 to 31 Mar 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Mar 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate11 Aug 2017View
Extension certificate1 Nov 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51900005526

Is Allana Mansion delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2019, revised to 31 Mar 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51900005526. The completion date moved from 31 Mar 2019 to 31 Mar 2024.

Who is the promoter?

MahaRERA records K. Living Estates Private Limited as the promoter of P51900005526.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900005526.

Answers are generated from the record.

Data through28 Oct 2026, 01:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology