P51900003595
Ruparel Vivanza · Ward E, Mumbai City · R R Builders
Promised for 30 Jun 2025, extended once to 31 Mar 2027, which is still ahead.
The revised date is 1 year and 9 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2025 to 31 Mar 2027 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51900003595
Is Ruparel Vivanza delayed?
Its completion moved from 30 Jun 2025 to 31 Mar 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P51900003595. The completion date moved from 30 Jun 2025 to 31 Mar 2027.
Who is the promoter?
MahaRERA records R R Builders as the promoter of P51900003595.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51900003595.
Answers are generated from the record.