Registered1 extensionMahaRERA status: Certificate Signed

P51900003595

Ruparel Vivanza · Ward E, Mumbai City · R R Builders

Promised for 30 Jun 2025, extended once to 31 Mar 2027, which is still ahead.

The revised date is 1 year and 9 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2025 to 31 Mar 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate29 Nov 2022View
Extension certificate15 Dec 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P51900003595

Is Ruparel Vivanza delayed?

Its completion moved from 30 Jun 2025 to 31 Mar 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51900003595. The completion date moved from 30 Jun 2025 to 31 Mar 2027.

Who is the promoter?

MahaRERA records R R Builders as the promoter of P51900003595.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900003595.