RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800077985
Rakyan Imperia · Vileparle, Mumbai Suburban · Rr Brickcon Llp
Promised for 30 Sep 2027, extended to 30 Jan 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2027 to 30 Jan 2028.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51800077985
Is Rakyan Imperia delayed?
Its completion moved from 30 Sep 2027 to 30 Jan 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51800077985. The completion date moved from 30 Sep 2027 to 30 Jan 2028.
Who is the promoter?
MahaRERA records Rr Brickcon Llp as the promoter of P51800077985.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800077985.
Answers are generated from the record.