Registered1 extensionMahaRERA status: Certificate Signed

P51800077267

The West · Malad, Mumbai Suburban · Liondale Skyscraper LLP

Promised for 31 Dec 2026, extended once to 30 Apr 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2026 to 30 Apr 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate19 Aug 2026View
Registration certificate24 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800077267

Is The West delayed?

Its completion moved from 31 Dec 2026 to 30 Apr 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800077267. The completion date moved from 31 Dec 2026 to 30 Apr 2027.

Who is the promoter?

MahaRERA records Liondale Skyscraper LLP as the promoter of P51800077267.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800077267.

Answers are generated from the record.

Data through28 Oct 2026, 03:05SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology