Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800055681

Arihant View · Kolekalyan, Mumbai Suburban · Arihant Labdhi Builders Private Limited

Promised for 31 Aug 2025 — that date has passed and MahaRERA does not mark the project complete.

1 year and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Aug 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Apr 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800055681

Is Arihant View delayed?

Yes. MahaRERA records a promised completion of 31 Aug 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800055681.

Who is the promoter?

MahaRERA records Arihant Labdhi Builders Private Limited as the promoter of P51800055681.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800055681.

Answers are generated from the record.

Data through29 Oct 2026, 02:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology