P51800054931
Manisha Heights · Andheri, Mumbai Suburban · K Anand Infra
Promised for 19 Jan 2028, extended to 19 May 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 19 Jan 2028 to 19 May 2028.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51800054931
Is Manisha Heights delayed?
Its completion moved from 19 Jan 2028 to 19 May 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51800054931. The completion date moved from 19 Jan 2028 to 19 May 2028.
Who is the promoter?
MahaRERA records K Anand Infra as the promoter of P51800054931.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800054931.