Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P51800054279

Sayba Orchid · Kurla, Mumbai Suburban · Star Rise

Promised for 31 Dec 2026; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 72

Encumbrance details24 Jun 2023View
Form B24 Jun 2023View
Other24 Jun 2023View
Other24 Jun 2023View
Encumbrance details24 Jun 2023View
Title report7 Aug 2023View
Commencement certificate7 Aug 2023View
Other7 Aug 2023View
Show all 72 documents
Other7 Aug 2023View
Allotment letter7 Aug 2023View
Other7 Aug 2023View
Other7 Aug 2023View
Other7 Aug 2023View
Other23 Dec 2023View
Commencement certificate5 Jan 2024View
Registration certificate15 Jan 2024View
Form 118 Oct 2024View
Commencement certificate13 Nov 2024View
Form 224 Dec 2024View
Form 224 Dec 2024View
Form 224 Dec 2024View
Form 121 Jan 2025View
Form 226 Feb 2025View
Other26 Feb 2025View
Other26 Feb 2025View
Other26 Feb 2025View
Other26 Feb 2025View
Form 116 Apr 2025View
Form 2A10 May 2025View
Form 212 Jun 2025View
Other12 Jun 2025View
Other12 Jun 2025View
Form 2A12 Jun 2025View
Form 2A12 Jun 2025View
Form 19 Sep 2025View
Form 29 Sep 2025View
Form 120 Jan 2026View
Other20 Jan 2026View
Other20 Jan 2026View
Other20 Jan 2026View
Other20 Jan 2026View
Other20 Jan 2026View
Other20 Jan 2026View
Other21 Jan 2026View
OtherView
Layout planView
Layout planView
Layout planView
Layout planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Allotment letterView
Layout planView
Layout planView
OtherView
Building planView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51800054279

Is Sayba Orchid delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2026.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800054279.

Who is the promoter?

MahaRERA records Star Rise as the promoter of P51800054279.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800054279.

Answers are generated from the record.

Data through29 Oct 2026, 02:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology