Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Lapsed

P51800052562

Garodia Nagar Mahavir Dham Chs Ltd · Kirol, Mumbai Suburban · Garodia Nagar Mahavir Dham Chs Ltd

Promised for 31 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.

10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Caution: 2 other MahaRERA orders name this registration.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 76

Form B10 Apr 2023View
Other10 Apr 2023View
Commencement certificate21 Apr 2023View
Encumbrance details21 Apr 2023View
Allotment letter21 Apr 2023View
Other21 Apr 2023View
Commencement certificate24 Apr 2023View
Encumbrance details28 Apr 2023View
Show all 76 documents
Encumbrance details28 Apr 2023View
Other11 May 2023View
Title report22 May 2023View
Other22 May 2023View
Other22 May 2023View
Registration certificate11 Sep 2023View
Form 18 Nov 2023View
Commencement certificate11 Mar 2024View
Form 111 Mar 2024View
Form 211 Mar 2024View
Commencement certificate12 Mar 2024View
Other12 Mar 2024View
Form 120 Mar 2025View
Form 54 Apr 2025View
Form 121 Apr 2025View
Form 221 Apr 2025View
Form 128 Apr 2025View
Other28 Apr 2025View
Other28 Apr 2025View
Other28 Apr 2025View
Form 131 Jul 2025View
Form 231 Jul 2025View
Other31 Jul 2025View
Form 52 Jun 2026View
Form 2A4 Aug 2026View
Form 2A4 Aug 2026View
Form 2A4 Aug 2026View
Form 56 Aug 2026View
Form 56 Aug 2026View
Form 110 Aug 2026View
Form 210 Aug 2026View
Other10 Aug 2026View
Form 120 Aug 2026View
Form 220 Aug 2026View
OtherView
OtherView
Layout planView
Layout planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 2

Questions about P51800052562

Is Garodia Nagar Mahavir Dham Chs Ltd delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800052562.

Who is the promoter?

MahaRERA records Garodia Nagar Mahavir Dham Chs Ltd as the promoter of P51800052562.

Is it on any MahaRERA regulatory list?

2 MahaRERA orders or lists name P51800052562.

Answers are generated from the record.

Data through25 Oct 2026, 03:14SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology