RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800047631

Palkhi Roha · Borivali, Mumbai Suburban · Ysd & Kcd Realty Llp

Promised for 2 Feb 2025 — that date has passed and MahaRERA does not mark the project complete.

1 year and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 2 Feb 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate31 Aug 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800047631

Is Palkhi Roha delayed?

Yes. MahaRERA records a promised completion of 2 Feb 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800047631.

Who is the promoter?

MahaRERA records Ysd & Kcd Realty Llp as the promoter of P51800047631.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800047631.