Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800045345

RAGHAV Paradise · Borivali, Mumbai Suburban · Veda Infra Projects

Promised for 31 Dec 2024, extended once to 30 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2024 to 30 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate28 Aug 2023View
Extension certificate28 Aug 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800045345

Is RAGHAV Paradise delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2024, revised to 30 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800045345. The completion date moved from 31 Dec 2024 to 30 Dec 2025.

Who is the promoter?

MahaRERA records Veda Infra Projects as the promoter of P51800045345.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800045345.

Answers are generated from the record.

Data through25 Oct 2026, 03:00SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology