RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800045230

Shanti Kishan CHS LTD · Borivali, Mumbai Suburban · Konark Structural Engineers Private Limited

Promised for 31 Dec 2024, extended once to 30 Jun 2025 — and that date has passed without the project marked complete on MahaRERA.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2024 to 30 Jun 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate10 Jul 2024View
Extension certificate11 Jul 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800045230

Is Shanti Kishan CHS LTD delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2024, revised to 30 Jun 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800045230. The completion date moved from 31 Dec 2024 to 30 Jun 2025.

Who is the promoter?

MahaRERA records Konark Structural Engineers Private Limited as the promoter of P51800045230.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800045230.