Registered1 extensionMahaRERA status: Certificate Signed

P51800031191

Mahakali Hills · Andheri, Mumbai Suburban · Mohid Construction Co

Promised for 31 Dec 2024, extended once to 31 Dec 2026, which is still ahead.

The revised date is 2 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2024 to 31 Dec 2026 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate7 Jan 2025View
Registration certificate18 Feb 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800031191

Is Mahakali Hills delayed?

Its completion moved from 31 Dec 2024 to 31 Dec 2026; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800031191. The completion date moved from 31 Dec 2024 to 31 Dec 2026.

Who is the promoter?

MahaRERA records Mohid Construction Co as the promoter of P51800031191.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800031191.