RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800030498
93 Palladian · Andheri, Mumbai Suburban · Vijayalaxmi Builders & Contractors
Promised for 30 Jun 2028, extended to 30 Oct 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2028 to 30 Oct 2028.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51800030498
Is 93 Palladian delayed?
Its completion moved from 30 Jun 2028 to 30 Oct 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51800030498. The completion date moved from 30 Jun 2028 to 30 Oct 2028.
Who is the promoter?
MahaRERA records Vijayalaxmi Builders & Contractors as the promoter of P51800030498.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800030498.
Answers are generated from the record.
