RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800028304

Platinum Casa Millennia · Andheri, Mumbai Suburban · Platinum Aashiana Llp

Promised for 30 Mar 2025 — that date has passed and MahaRERA does not mark the project complete.

1 year and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Mar 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800028304

Is Platinum Casa Millennia delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800028304.

Who is the promoter?

MahaRERA records Platinum Aashiana Llp as the promoter of P51800028304.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800028304.

Answers are generated from the record.

Data through30 Oct 2026, 02:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology