Completed

P51800023099

Savana · Borivali, Mumbai Suburban · Simba Properties Llp

Promised for 30 Jun 2023; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 66

Commencement certificate12 Nov 2019View
Form B13 Nov 2019View
Form 213 Nov 2019View
Form 122 Nov 2019View
Allotment letter22 Nov 2019View
Title report27 Nov 2019View
Encumbrance details27 Nov 2019View
Allotment letter27 Nov 2019View
Show all 66 documents
Allotment letter18 Feb 2020View
Allotment letter18 Feb 2020View
Form 2A11 Mar 2020View
Form 210 Aug 2020View
Form 18 Sep 2020View
Form 18 Sep 2020View
Form 219 Sep 2020View
Form 51 Oct 2020View
Form 13 Nov 2020View
Form 23 Nov 2020View
Encumbrance details9 Dec 2020View
Form B30 Dec 2020View
Form 121 Jan 2021View
Form 222 Jan 2021View
Form 119 Apr 2021View
Form 24 May 2021View
Form 51 Jul 2021View
Commencement certificate12 Jul 2021View
Form 14 Aug 2021View
Other16 Nov 2021View
Form 119 Nov 2021View
Form 19 Feb 2022View
Form 29 Feb 2022View
Form 120 May 2022View
Form 220 May 2022View
Other26 Jul 2022View
Form 15 Aug 2022View
Form 25 Aug 2022View
Form 25 Aug 2022View
Other12 Aug 2022View
Commencement certificate18 Aug 2022View
Form 2A25 Aug 2022View
Form 515 Oct 2022View
Form 231 Oct 2022View
Form 14 Nov 2022View
Form 222 Dec 2022View
Form 222 Dec 2022View
Occupancy / completion certificate22 Dec 2022View
Other20 Jan 2023View
Other20 Jan 2023View
Other20 Jan 2023View
Other20 Jan 2023View
Form 424 Jan 2023View
Registration certificate4 May 2023View
Form 527 Sep 2023View
OtherView
OtherView
Layout planView
Layout planView
Layout planView
Building planView
Building planView
Building planView
Building planView
OtherView
Allotment letterView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51800023099

Is Savana delayed?

MahaRERA reports it completed. Its promised completion date was 30 Jun 2023.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800023099.

Who is the promoter?

MahaRERA records Simba Properties Llp as the promoter of P51800023099.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800023099.

Answers are generated from the record.

Data through30 Oct 2026, 02:30SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology