RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Completed
P51800022067
Vicino A3a4 · Andheri, Mumbai Suburban · Mahindra Lifespace Developers Limited
Promised for 30 Mar 2025; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 78
Orders 0
No MahaRERA order or list names this number.
Questions about P51800022067
Is Vicino A3a4 delayed?
MahaRERA reports it completed. Its promised completion date was 30 Mar 2025.
How many extensions has it had?
Deedo holds 0 extension certificates for P51800022067.
Who is the promoter?
MahaRERA records Mahindra Lifespace Developers Limited as the promoter of P51800022067.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800022067.
Answers are generated from the record.
Data through25 Oct 2026, 02:33SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology