Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Lapsed

P51800020798

Puneet Prime · Kurla, Mumbai Suburban · Puneet Builders

Promised for 30 Jun 2025 — that date has passed and MahaRERA does not mark the project complete.

1 year and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: The latest completion date on record, 30 Jun 2025, has passed.

Documents 88

Title report26 Apr 2019View
Form B26 Apr 2019View
Form 126 Apr 2019View
Allotment letter26 Apr 2019View
Encumbrance details26 Apr 2019View
Form 226 Apr 2019View
Commencement certificate19 Aug 2019View
Form 2A2 Jan 2020View
Show all 88 documents
Form 2A2 Jan 2020View
Form 2A2 Jan 2020View
Form 2A3 Jan 2020View
Other4 Jul 2020View
Other4 Jul 2020View
Encumbrance details17 Jul 2020View
Title report19 Feb 2021View
Other19 Feb 2021View
Other19 Feb 2021View
Other19 Feb 2021View
Form 2A23 Feb 2021View
Form 54 Mar 2021View
Commencement certificate30 Mar 2021View
Form 2A25 May 2021View
Form 215 Aug 2021View
Form 27 Oct 2021View
Form 531 Dec 2021View
Commencement certificate21 Jan 2022View
Form 119 Mar 2022View
Form 219 Mar 2022View
Form 228 Sep 2022View
Form 228 Sep 2022View
Form 112 Oct 2022View
Commencement certificate12 Oct 2022View
Form 112 Oct 2022View
Form 514 Oct 2022View
Form 2A15 Oct 2022View
Form 221 Oct 2022View
Form 119 Jan 2023View
Form 29 Feb 2023View
Form 118 May 2023View
Form 126 Jul 2023View
Form 25 Sep 2023View
Form 25 Sep 2023View
Encumbrance details2 Dec 2023View
Form 110 Jan 2024View
Form 111 Jan 2024View
Form 212 Feb 2024View
Form 212 Feb 2024View
Form 2A27 Feb 2024View
Form 527 Mar 2024View
Form 115 Apr 2024View
Form 215 Jun 2024View
Commencement certificate17 Jun 2024View
Form 110 Jul 2024View
Registration certificate22 Jul 2024View
Form 17 Oct 2024View
Form 27 Oct 2024View
Form 517 Dec 2024View
Form 117 Jan 2025View
Form 227 Mar 2025View
Form 22 Apr 2025View
Form 14 Apr 2025View
Form 22 May 2025View
Form 2A16 May 2025View
Form 2A16 May 2025View
Form 13 Sep 2025View
Other3 Sep 2025View
Form 23 Sep 2025View
Other3 Sep 2025View
Form 53 Dec 2025View
OtherView
Layout planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
OtherView
OtherView
Layout planView
Building planView
Building planView
Building planView

Orders 0

No MahaRERA order or list names this number.

Questions about P51800020798

Is Puneet Prime delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800020798.

Who is the promoter?

MahaRERA records Puneet Builders as the promoter of P51800020798.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800020798.

Answers are generated from the record.

Data through22 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology