Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800013616

ZIA Complex Wing E · Kurla, Mumbai Suburban · I. R. Construction

Promised for 30 Mar 2022, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

4 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Mar 2022 to 31 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate16 Oct 2017View
Extension certificate15 Oct 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800013616

Is ZIA Complex Wing E delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2022, revised to 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800013616. The completion date moved from 30 Mar 2022 to 31 Dec 2025.

Who is the promoter?

MahaRERA records I. R. Construction as the promoter of P51800013616.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800013616.

Answers are generated from the record.

Data through29 Oct 2026, 02:01SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology