Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P51800012209

Siddhi Vinayak · Borivali, Mumbai Suburban · Shree Ganesh Enterprises

Promised for 30 Dec 2026, extended to 30 Apr 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2026 to 30 Apr 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800012209

Is Siddhi Vinayak delayed?

Its completion moved from 30 Dec 2026 to 30 Apr 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800012209. The completion date moved from 30 Dec 2026 to 30 Apr 2027.

Who is the promoter?

MahaRERA records Shree Ganesh Enterprises as the promoter of P51800012209.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800012209.

Answers are generated from the record.

Data through28 Oct 2026, 01:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology