Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800011662

Serendipity At BKC · Andheri, Mumbai Suburban · Forum Homes Pvt Ltd

Promised for 31 Dec 2019, extended once to 31 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 31 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate31 Aug 2017View
Extension certificate8 Jun 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800011662

Is Serendipity At BKC delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800011662. The completion date moved from 31 Dec 2019 to 31 Dec 2024.

Who is the promoter?

MahaRERA records Forum Homes Pvt Ltd as the promoter of P51800011662.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800011662.

Answers are generated from the record.

Data through25 Oct 2026, 02:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology