RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800011066
Siddhivinayak · Borivali, Mumbai Suburban · Triumph Ventures
Promised for 30 Jun 2021, extended once to 31 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.
5 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2021 to 31 Dec 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Dec 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800011066
Is Siddhivinayak delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 31 Dec 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800011066. The completion date moved from 30 Jun 2021 to 31 Dec 2023.
Who is the promoter?
MahaRERA records Triumph Ventures as the promoter of P51800011066.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800011066.
Answers are generated from the record.
