Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800010732

Zee Swastik · Andheri, Mumbai Suburban · Zee Rpm Builders And Developers Llp

Promised for 30 Dec 2021 — that date has passed and MahaRERA does not mark the project complete.

4 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800010732

Is Zee Swastik delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800010732.

Who is the promoter?

MahaRERA records Zee Rpm Builders And Developers Llp as the promoter of P51800010732.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800010732.

Answers are generated from the record.

Data through25 Oct 2026, 02:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology