Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800009405

Redevelopment Of Tilak Nagar Nisarg Co. Op. Hsg. Soc. Ltd. · Kurla, Mumbai Suburban · Reliance Realtors & Estate Developers

Promised for 30 Dec 2020, extended once to 30 Mar 2022 — and that date has passed without the project marked complete on MahaRERA.

5 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2020 to 30 Mar 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Mar 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800009405

Is Redevelopment Of Tilak Nagar Nisarg Co. Op. Hsg. Soc. Ltd. delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2020, revised to 30 Mar 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800009405. The completion date moved from 30 Dec 2020 to 30 Mar 2022.

Who is the promoter?

MahaRERA records Reliance Realtors & Estate Developers as the promoter of P51800009405.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800009405.

Answers are generated from the record.

Data through25 Oct 2026, 02:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology